Incinerator supply
Submitted by gillis.winderickx on Fri, 06/16/2017 - 12:31
Answer to the question:
It depends on different factors, like:
- the complexity of the plant (mainly energy recovery),
- a new or tailor made installation, or an incinerator which has already all drawings ready
- People: all drawers and engineers available? Or occupied with an other order?
- Suppliers: are they ready?
- Etc.
Generally:
- Drawings : 2 - 4 or more months
- Equipment supply : 4 - 7 months
- Assembly (also during equipment supply) : 4 months
- Start-up : 2 months
- Fine tuning : 2 months
- Guarantee
For a small incineration plant you may count 12 - 14 months
For a big incineration plant you may count 24 months or more.