Incinerator supply

Answer to the question: 

It depends on different factors, like:

  • the complexity of the plant (mainly energy recovery),
  • a new or tailor made installation, or an incinerator which has already all drawings ready
  • People: all drawers and engineers available? Or occupied with an other order?
  • Suppliers: are they ready?
  • Etc.

Generally:

  1. Drawings : 2 - 4 or more months
  2. Equipment supply : 4 - 7 months
  3. Assembly (also during equipment supply) : 4 months
  4. Start-up : 2 months
  5. Fine tuning : 2 months
  6. Guarantee

For a small incineration plant you may count 12 - 14 months
For a big incineration plant you may count 24 months or more.